Substation Automation Systems (SAS): Testing, Commissioning & Best Practices

What is a Substation Automation System (SAS)?

Think of a Substation Automation System (SAS) as the “brain” of a modern electrical substation. Just like your smartphone controls different apps and features automatically, SAS controls and monitors everything happening in an electrical substation without needing people to manually flip switches or check meters constantly.

In simple terms, SAS is a network of smart devices, computers, and communication cables that work together to:

  • Monitor electricity flow automatically
  • Control equipment remotely
  • Protect the system from faults
  • Record what’s happening 24/7
  • Alert operators when something goes wrong

Why Do We Need Substation Automation System (SAS)?

Old substations required workers to physically walk around, check meters, and manually operate switches. This was time-consuming, risky, and mistakes could happen. Modern SAS solves these problems by:

Making Operations Faster: Computers respond in milliseconds, much faster than humans.

Improving Safety: Workers can control equipment from a safe control room instead of working near high-voltage equipment.

Preventing Blackouts: The system detects problems instantly and can fix them automatically before you even notice.

Saving Money: One operator can monitor multiple substations from a single location.

Better Record Keeping: Everything is recorded digitally, making it easy to find out what happened during a fault or outage.

Main Parts of a Substation Automation System (SAS)

Let’s break down the SAS into simple parts you can understand:

The Control Room Equipment

SCADA Servers – The Main Computer Brain

These are powerful computers that collect information from all the equipment in the substation. Think of them as the “command center” that knows everything happening at any moment. Most systems have two servers – if one fails, the backup takes over automatically so nothing stops working.

Operator Workstations – The Dashboard

These are special computer screens where operators watch the substation. They show:

  • Which equipment is running
  • Current and voltage measurements
  • Alarms when something goes wrong
  • Buttons to control switches and breakers

It’s like the dashboard in your car, but for a power substation.

Engineering Workstation – The Technician’s Laptop

This is a specialized computer that engineers use to:

  • Change device settings
  • Download fault records
  • Update software
  • Fix problems

Think of it as the “settings menu” for the entire system.

Communication Gateways – The Translators

These devices convert data from one language to another. The substation equipment “speaks” one language (IEC 61850), but the main control center might “speak” a different language (DNP3). Gateways translate between them so everyone can communicate.

Equipment in the Field

Intelligent Electronic Devices (IEDs) – The Smart Sensors

These are like smart sensors placed on each piece of equipment (transformers, circuit breakers, etc.). They:

  • Measure voltage, current, and power
  • Protect equipment by opening breakers when faults occur
  • Send data to the control room
  • Receive commands from operators

Modern IEDs are like smartphones – they can do many jobs that used to require separate devices.

Ethernet Switches – The Traffic Controllers

Just like internet routers in your home, these switches direct data traffic between all the devices. They make sure information gets to the right place quickly and reliably.

Supporting Equipment

GPS Clock – The Timekeeper

Accurate timing is crucial in power systems. GPS clocks ensure every device has exactly the same time, down to the millisecond. This helps engineers figure out exactly when and where a fault happened.

Fiber Optic Cables – The Super-Fast Data Highway

These are special glass cables that send data using light instead of electricity. They’re faster than copper wires and aren’t affected by electrical interference from power equipment.

Backup Power Supplies – The Battery Backup

UPS (Uninterruptible Power Supply) systems keep the SAS running even when there’s a power outage. They work like a giant battery backup for your computer.

How to Set Up and Test the SAS (Commissioning Process)

Setting up an SAS is like building and testing a house – you need to follow steps carefully to make sure everything works.

Before You Start (Prerequisites)

Before testing begins, you need:

All the Paperwork: Drawings, manuals, IP addresses, test plans – everything must be ready and approved.

Physical Installation Complete: All equipment installed, cables connected, and panels closed.

Safety Equipment: Hard hats, safety glasses, insulated gloves, and proper warning tags on equipment.

Testing Individual Devices (IED Testing)

Think of this as checking each appliance in a house before moving in.

Step 1: Visual Check

Walk around and look at everything:

  • Is the device damaged?
  • Is it mounted correctly?
  • Are wires connected properly?
  • Is grounding in place?

Step 2: Check the Wiring

Like checking if your TV cables are plugged into the right ports:

  • Verify every wire goes to the correct terminal
  • Check fiber optic cables are connected
  • Test that power supplies work
  • Look for any loose connections

Step 3: Check the Settings

Turn on the device and verify:

  • Correct model and version
  • Right IP address (like checking your WiFi settings)
  • Proper configuration loaded
  • All features activated that you paid for

Step 4: Test the Functions

Testing Inputs: Send test signals to the device and make sure it sees them correctly. Like pressing doorbell and checking if it rings.

Testing Outputs: Command the device to close or open contacts and verify it actually does. Like turning on a light switch and checking if the light comes on.

LED Lights: Check that indicator lights show the right colors and meanings.

Testing the Communication Network

This is like testing your home WiFi to make sure all devices can talk to each other.

Fiber Optic Cable Testing

Special equipment tests if light signals travel properly through the fiber cables. Technicians measure:

  • Signal strength at the beginning
  • Signal strength at the end
  • Loss in between (should be minimal)

If the signal loss is too high, there might be a bad connection or damaged cable.

Network Switch Testing

Verify that data flows correctly through network switches:

  • All connections working
  • Unused ports turned off (for security)
  • Redundancy features enabled

System-Wide Testing

Now test if everything works together as a complete system.

Measurement Testing

Technicians inject known values of current and voltage into the system, then check if:

  • The IED shows the correct reading
  • The operator screen shows the same value
  • The main control center sees the same number

All three should match within acceptable limits.

Safety Interlock Testing

Safety interlocks prevent dangerous situations. For example, testing that:

  • You can’t close a breaker if ground switch is closed
  • You can’t open a disconnect switch when current is flowing
  • Alarms sound when they should

This is like testing that you can’t start your car when it’s in gear.

Redundancy Testing

Test the backup systems work:

  • Unplug the main server – backup should take over
  • Disconnect a network cable – traffic should reroute
  • Simulate equipment failure – system should continue working

Think of it like testing your spare tire before a road trip.

Testing Support Equipment

GPS Testing: Make sure all devices show exactly the same time.

Printer Testing: Verify alarms and reports print correctly.

Monitor Testing: Check all displays work properly.

Best Practices: Tips from Experts

Keep Good Records

Write everything down:

  • Take photos of installations
  • Save all test results
  • Keep backup copies of configurations
  • Document any changes made

Control Who Can Make Changes

Like password-protecting your phone:

  • Only trained people should change settings
  • Require approval for major changes
  • Keep a log of who changed what and when

Protect Against Hackers

Modern substations need cybersecurity:

  • Use strong passwords
  • Install firewalls
  • Keep software updated
  • Limit remote access

Regular Maintenance

Check systems regularly:

  • Review alarm logs
  • Test communication links
  • Update old equipment
  • Train operators on new features

Common Problems and How to Fix Them

Communication Lost

Problem: Devices stop talking to each other.

Common Causes:

  • Broken fiber cable (someone dug it up or equipment moved)
  • Wrong IP address settings
  • Failed network switch

How to Fix: Check physical connections first, then verify settings, then replace faulty equipment.

Wrong Time on Devices

Problem: Different devices show different times.

Why It Matters: Makes it impossible to figure out the sequence of events during a fault.

Common Causes:

  • GPS antenna blocked or damaged
  • Network settings wrong
  • Software needs update

How to Fix: Check GPS antenna, verify all devices are set to use GPS time, restart time sync service.

Measurements Don’t Match

Problem: The IED shows one reading, but the operator screen shows something different.

Common Causes:

  • Wrong wiring to sensors
  • Incorrect configuration
  • Communication error
  • Scaling factor wrong

How to Fix: Verify wiring first, then check configuration settings, then test communication path.

The Future of Substation Automation System (SAS)

Smarter Systems with AI

Future systems will use artificial intelligence to:

  • Predict when equipment will fail before it breaks
  • Automatically detect unusual patterns
  • Suggest optimal settings
  • Learn from past events

Better Security

As hackers get smarter, so must the defenses:

  • Advanced intrusion detection
  • Encrypted communications
  • Better access controls
  • Continuous security monitoring

Integration with Renewable Energy

SAS will manage:

  • Solar panel farms
  • Wind turbines
  • Battery storage systems
  • Electric vehicle charging stations

Conclusion

Substation Automation Systems have revolutionized how we manage electrical power. What used to require dozens of workers can now be monitored and controlled by a few operators from a central location. The system works 24/7, responds faster than humans, and keeps detailed records of everything.

For anyone working with electrical substations, understanding SAS is essential. The key is following proper testing procedures, maintaining good documentation, and keeping systems secure. While the technology is complex, breaking it down into these simple concepts makes it easier to understand and work with.

Whether you’re an engineer, technician, or operator, taking time to properly commission and maintain SAS equipment ensures reliable power delivery to homes and businesses. As technology advances, these systems will become even smarter and more capable, but the fundamental principles remain the same: monitor, protect, control, and record.


Learn More About Related Topics:

Helpful External Resources:

Explore the world of elctrical substation faults and troubleshooting. Our blogs provides valueable insights,tips and guides to help you understand and address various issues in substation operations.

Follow me

© 2025 — Substationfaults, All Rights Reserved

Scroll to Top